Practical Advice: COVID-19's Impact on the Construction Industry

Client Alert

As a member of the American Bar Association, Forum on the Construction Industry, BMD participated in a COVID-19 Construction Leadership Roundtable discussion with over 450 other construction attorneys representing nearly every voice in the industry. Here is the top practical advice and key takeaways: 

  1. Safety. Safety is the overriding imperative on all construction projects. Employers should designate and empower a COVID-19 Compliance Coordinator and post on site the CDC guidelines in English and other appropriate languages. The six-foot social distancing requirement, portable handwashing, wearing gloves, prohibiting carpooling to the jobsite, and closing jobsites to the public are now considered best practices and mandatory expectations for all employers. In some states, governmental agencies are spot checking jobsites and removing individuals who are not in compliance with the CDC guidelines. The Occupational Safety and Health Administration has issued guidance for protecting employees against workplace exposures to COVID-19. Employers should also be aware of OSHA standards which may apply to workplace exposures and when a case of COVID-19 is OSHA recordable. Learn more here from BMD’s March 20, 2020 OSHA and COVID-19: Workplace Exposures, Citations and Recording Client Advisory. 
  1. Notice. Give notice early and often! After providing notice, follow up with timely reports, cost information and detailed schedule impact data. Maintain detailed records if you want to preserve any chance of recovering for delay impacts. It is not enough to generally argue that your work has been delayed by COVID-19. It must be written in a way to prevent or discourage escalation, including litigation. Be prepared to demonstrate how and when delay impacts occurred, such as utilization of a measured mile analysis to prove loss of efficiency and productivity. Helping the owner or general contractor understand the unique circumstances which caused the delay will increase your chances to cooperatively resolve the problem. 
  1. Suspension or Termination of Work. Suspension or termination of work remains an option on a case-by-case basis. Work is generally proceeding but is being impacted by CDC guidelines. Each project is unique and requires the owner’s willingness to work with prime contractors, subcontractors, suppliers, and design professionals. It has been rare for attorneys to counsel clients to stop work. There have been some suspensions of work, but often work resumes if employers and workers take appropriate CDC precautions. For example, work is proceeding at the City of Tampa, Florida airport where virtual inspections are being conducted by using affidavits, video or digital images, or in-person inspections per CDC guidelines. Some third-party inspections have been allowed and some government agencies are deferring inspections. Materials onsite are being sanitized. By contrast, due to the large number of coronavirus cases in New York and New Jersey, most private and public construction projects in those areas have been shut down. 
  1. Collaboration. Because the phrase “unchartered waters” does not begin to describe the impact that COVID-19 is having on construction projects, the best advice for prime contractors and subcontractors is to try to row in the same direction. This is no time for battles or disputes between general contractors and subcontractors. Prime contractors should ascertain the cash flow status of their subcontractors to determine whether they will be able to perform under the current revenue-starved environment. A key element for project success is that all parties need to work together to identify risks, loss of productivity, schedule impacts, supply chain issues, safety issues, etc. In fact, it has been perceived that many owners are being more forgiving on product substitutions and developing creative solutions to deal with impacts resulting from coronavirus delays – so take advantage of it while you can by being collaborative! 
  1. Liquidated Damages, Force Majeure, and Excusable Delays. How courts will interpret construction contract delay clauses, force majeure clauses and common law rights with respect to the delay impacts associated with COVID-19 remains to be seen, and it will likely be determined on a case-by-case basis. Because many courts are holding civil disputes in abeyance, immediate relief from the judicial system is unlikely. For this reason, as well as solid business judgment, it makes good sense for the parties to cooperatively engage in direct and timely discussions regarding how to proceed with construction and manage delay impacts in a mutually beneficial way. Issuance of change orders or schedule extensions may relieve some of the time and cost impacts. Prudent owners welcome timely notice because they can attempt to manage these issues and risks. Excellent communication is the key to identify problems. Deliver timely written notice and detailed substantive documentation, offer creative solutions, and try to manage the difficult circumstances together. Rather than pulling the trigger on default clauses, it is generally advisable to push across the project finish line and properly document all cost and time impacts. As we advised in the BMD Client Advisory on March 17th, the extent to which COVID-19 excuses or extends contractual obligation(s) is a fact-specific determination that will depend on the nature of the obligations and the specific language of the contract. 
  1. Project Financing. “Cash is king,” and if the availability of private and public funding is impaired, work may cease and sureties may be required to take over on payment and performance bonded projects. Conduct adequate due diligence before committing to business relationships. On an ongoing basis, be sure to request and receive adequate assurances of financial ability to pay whenever possible. 

Please feel free to reach out to Bob Hager, Justin Alaburda, David Scott, Jeff Miller, Steve Matasich or Brandon Pauley if you have any questions or comments on these issues. This is intended as general advice and should not be interpreted as legal advice. Each situation is unique and requires specific analysis of relevant contracts, facts and legal obligations.


Vacating, Modifying or Correcting an Arbitration Award Under R.C. 2711.13: Three-Month Limitation Maximum; Not Guaranteed Amount of Time

In a recent decision, the Supreme Court of Ohio held that neither R.C. 2711.09 nor R.C. 2711.13 requires a court to wait three months after an arbitration award is issued before confirming the award. R.C. 2711.13 provides that “after an award in an arbitration proceeding is made, any party to the arbitration may file a motion in the court of common pleas for an order vacating, modifying, or correcting the award.” Any such motion to vacate, modify, or correct an award “must be served upon the adverse party or his attorney within three months after the award is delivered to the parties in interest.” In BST Ohio Corporation et al. v. Wolgang, the Court held the three-month period set forth in R.C. 2711.13 is not a guaranteed time period in which to file a motion to vacate, modify, or correct an arbitration award. 2021-Ohio-1785.

EEOC Provides Updated Guidance Regarding Employer COVID-19 Vaccine Policies

On May 28, 2021, the U.S. Equal Employment Opportunity Commission updated its guidance regarding employer COVID-19 vaccination policies. The new guidance provides much-needed clarification of expectations for employers seeking to promote workplace safety and prevent the spread of COVID-19, including discussion of mandatory vaccination policies, voluntary vaccination incentives, and accommodation of employees based on disability or sincerely held religious beliefs. The full text of the update is found in Section K of the EEOC’s COVID Q&A document. You can also learn more about these and other developments from BMD's Bryan Meek and Monica Andress through the Employment Law After Hours YouTube channel, available here.

What Telemedical Barriers Practices Face and How They Can Manage Them

The onset of the COVID-19 pandemic has led to many businesses and industries having to rapidly adapt new practices in order to stay profitable, and the healthcare industry is no exception. Although telehealth tools and practices have existed and been used since the Vietnam War, the pandemic has caused many individual healthcare practices to heavily rely on telehealth as a large portion of their service mix in order to continue to provide care for patients. Because of this rapid adoption of telehealth practices in order to combat the restrictions of COVID-19, the telemedicine industry’s revenue has exploded in the last year. Experts predict that telehealth will continue to grow in use beyond the current pandemic, estimating the industry’s worth to be $25 billion by 2025. However, this rapid adoption of telehealth was prompted out of need and has not been without its own barriers that practices now face.

Which Entity Should I Form When Starting a New Business?

As a tax law attorney, friends and acquaintances ask me this question all the time: what type of entity should I form when starting a new business? With many business options available it can be confusing determining which business structure would be appropriate. Below is a general overview of each business structure and the tax responsibilities of each.

IMPORTANT UPDATE: IRS Opens Portals for Advanced Child Tax Credit Payments 2021

The American Rescue Plan Act (the “Act”) expands the Child Tax Credit for tax year 2021. In addition to expanding the Child Tax Credit, the Act provides for advance payments of the 2021 Child Tax Credit. Beginning in July, the IRS will automatically send Advanced Child Tax Credit payments to eligible taxpayers based on their 2020 tax return (or 2019 tax return if the 2020 tax return has not been filed and processed yet). The amount of the advanced payment will be up to $300 each month for each qualifying child under 6 years old at the end of 2021 and $250 each month for each qualifying child between 6 and 17 years old at the end of 2021. For example, if you have 2 qualifying children, one 4 years old and one 8 years old, you may receive up to $550 each month in advance child tax credit payments.