Resources

Client Alerts, News Articles, Blog Posts, & Multimedia

Everything you need to know about BMD and the industry.

Ohio Supreme Court Liquidated Damages Analysis: Hindsight is not 2020!

News Article

In a case decided on February 24, 2016, the Ohio Supreme Court construed the enforceability of a liquidated damages provision in a public works construction contract. The Court held that when evaluating the enforceability of a liquidated damages provision in a construction contract, the court must conduct its analysis prospectively, based on the per diem amount of the liquidated damages at the time the contract is executed, and not retrospectively, based on the total amount of liquidated damages that ultimately accrue.

In reversing the Court of Appeals, the Ohio Supreme Court determined that the mere fact that the liquidated damages totaled $277,900 (calculated at $700 per day times 397 days late) did not result in a finding that the amount of liquidated damages was unreasonable where the base contract amount was $683,300. The flaw in the Court of Appeals reasoning was that it applied a retrospective analysis using hindsight. The long-standing test in Ohio requires the analysis to be considered at the time the parties entered into the contract.

The Ohio Supreme Court also held that “liquidated damages are not deemed a penalty simply because a project consists of new construction of an improvement that did not exist previously and no proof of damages is required to enforce liquidated damages pursuant to such a contract.”

This decision also includes an interesting overview of the Samson Sales tripartite test for distinguishing between an unenforceable penalty clause and a valid liquidated damages clause.

To read the Slip Op. No. 2016-Ohio-628, Boone Coleman Constr., Inc., v. Piketon, visit: http://www.supremecourt.ohio.gov/rod/docs/pdf/0/2016/2016-Ohio-628.pdf

Should you wish to consult with the author of this article, please feel free to contact Attorney Robert A. Hager at (330) 253–4925.


BMD Strengthens Presence with New Office in Canton, Ohio

CANTON, OHIO - Brennan Manna Diamond, LLC, a full-service law firm based in Akron, Ohio and with more than 70 attorneys, is expanding to Stark County. We are pleased to announce that we have opened a new office in Canton, Ohio. The new office is located at: 4518 Fulton Road, Suite 202, Canton, OH 44718.

FTC Supports Retiring the Ohio APRN Collaborative Agreement

As an industry leading advocate and general counsel for the Ohio Association of Advanced Practice Nurses, Brennan, Manna & Diamond attorney, Jeana M. Singleton, has been integral in efforts to bring an outdated regulatory structure into the 21st century by modernizing the law and expanding access to care.

BMD Congratulates 2020 Ohio Super Lawyers and Ohio Rising Stars

BRENNAN, MANNA & DIAMOND is proud to announce RICHARD W. BURKE (Estate Planning and Probate),HAMILTON DeSAUSSURE, JR. (Business Litigation), ROBERT A. HAGER (Construction Litigation), DAVID J. HRINA (Business/Corporate), MICHAEL A. STEEL (Bankruptcy, Business) and RICHARD L. WILLIGER (Workers’ Compensation) have been selected as 2020 Ohio Super Lawyers by Law and Politics magazine, Northern Ohio Live magazine, and Cincinnati Magazine in their respective area of practice. BMD’s 2020 Rising Stars include: JUSTIN M. ALABURDA (Business Litigation), KYLE A. JOHNSON (Business Litigation), ALEX J. McCALLION (Business Litigation), CHRISTOPHER J. MEAGER (State/Local/Muni Law), BRANDON T. PAULEY (Business/Corporate) and DANIEL J. RUDARY (Business Litigation)

Ohio's "One Bite" Program Changes

The Ohio Medical Board has for some years had a “One Bite” program where a physician with a substance problem could undergo treatment. The treatment was private and not disclosed to the Medical Board. If the problem was later disclosed, the physician obtaining treatment would avoid sanctions from the Medical Board.

Jury Awards Care Center $225,000

Congratulations to Scott Sandrock on the jury verdict in favor of our client. The verdict stems from the lawsuit filed on behalf of our client against Spectrum Cable for fraud in connection with business services. The jury awarded Plaintiff $22,000 for compensatory damages, plus $225,000 in punitive damages and recovery of attorney fees in favor of our client.