Resources

Client Alerts, News Articles, Blog Posts, & Multimedia

Everything you need to know about BMD and the industry.

Ohio Supreme Court Liquidated Damages Analysis: Hindsight is not 2020!

News Article

In a case decided on February 24, 2016, the Ohio Supreme Court construed the enforceability of a liquidated damages provision in a public works construction contract. The Court held that when evaluating the enforceability of a liquidated damages provision in a construction contract, the court must conduct its analysis prospectively, based on the per diem amount of the liquidated damages at the time the contract is executed, and not retrospectively, based on the total amount of liquidated damages that ultimately accrue.

In reversing the Court of Appeals, the Ohio Supreme Court determined that the mere fact that the liquidated damages totaled $277,900 (calculated at $700 per day times 397 days late) did not result in a finding that the amount of liquidated damages was unreasonable where the base contract amount was $683,300. The flaw in the Court of Appeals reasoning was that it applied a retrospective analysis using hindsight. The long-standing test in Ohio requires the analysis to be considered at the time the parties entered into the contract.

The Ohio Supreme Court also held that “liquidated damages are not deemed a penalty simply because a project consists of new construction of an improvement that did not exist previously and no proof of damages is required to enforce liquidated damages pursuant to such a contract.”

This decision also includes an interesting overview of the Samson Sales tripartite test for distinguishing between an unenforceable penalty clause and a valid liquidated damages clause.

To read the Slip Op. No. 2016-Ohio-628, Boone Coleman Constr., Inc., v. Piketon, visit: http://www.supremecourt.ohio.gov/rod/docs/pdf/0/2016/2016-Ohio-628.pdf

Should you wish to consult with the author of this article, please feel free to contact Attorney Robert A. Hager at (330) 253–4925.


Attorney Monica Andress Selected as an Emerging Leader in the Torchbearers Akron Class of 2023

Monica Andress selected to Torchbearers Akron Class of 2023.

Brennan Manna Diamond Announces Firmwide Attorney Promotions

Business law firm, Brennan, Manna & Diamond (BMD) is pleased to announce 2023 Attorney promotions throughout the firm. Kathryn (Kate) Hickner has been named as BMD’s Cleveland Office Managing Partner. The following BMD attorneys were promoted to Member of the firm, effective December 1: Randal Fairbanks, Donna Flammang, Kyle Johnson, Christopher CJ Meager. Additionally, the following BMD attorneys were promoted to Partner, effective December 1: Elizabeth Shively Boatwright, Mathew Doney, Alicia Kupcinskas, Cassandra Manna, Ashley Watson. Nathan Altstadt, Morgan Carr, Jillian Chapman, Jacob David, Kelly Jena, and Rachel Stermer have joined the firm as new attorneys.

BMD Names Kathryn Hickner to Cleveland Office Managing Partner, the Firm’s First Female Attorney Appointed to Role

Kathryn E. Hickner Promoted to Cleveland Office Managing Partner with Brennan Manna & Diamond

Recent Litigation Challenges the Affordable Care Act Preventive Services Requirement

The Affordable Care Act (ACA) has been met with numerous legal challenges. The most recent legal challenge, Braidwood Management Inc. v. Becerra, could affect millions of people covered by private health insurance.

BMD’s Director of Marketing Jennifer Shankleton Elected as President of the LMA Midwest Region for 2023

Congratulations to Jennifer Shankleton, BMD’s Director of Marketing, on her recent election to President of the Legal Marketing Association (LMA) Midwest Region for 2023!  LMA is a premier professional association focused on empowering marketing, business development, and client service professionals.