Ohio Supreme Court Liquidated Damages Analysis: Hindsight is not 2020!

News Article

In a case decided on February 24, 2016, the Ohio Supreme Court construed the enforceability of a liquidated damages provision in a public works construction contract. The Court held that when evaluating the enforceability of a liquidated damages provision in a construction contract, the court must conduct its analysis prospectively, based on the per diem amount of the liquidated damages at the time the contract is executed, and not retrospectively, based on the total amount of liquidated damages that ultimately accrue.

In reversing the Court of Appeals, the Ohio Supreme Court determined that the mere fact that the liquidated damages totaled $277,900 (calculated at $700 per day times 397 days late) did not result in a finding that the amount of liquidated damages was unreasonable where the base contract amount was $683,300. The flaw in the Court of Appeals reasoning was that it applied a retrospective analysis using hindsight. The long-standing test in Ohio requires the analysis to be considered at the time the parties entered into the contract.

The Ohio Supreme Court also held that “liquidated damages are not deemed a penalty simply because a project consists of new construction of an improvement that did not exist previously and no proof of damages is required to enforce liquidated damages pursuant to such a contract.”

This decision also includes an interesting overview of the Samson Sales tripartite test for distinguishing between an unenforceable penalty clause and a valid liquidated damages clause.

To read the Slip Op. No. 2016-Ohio-628, Boone Coleman Constr., Inc., v. Piketon, visit: http://www.supremecourt.ohio.gov/rod/docs/pdf/0/2016/2016-Ohio-628.pdf

Should you wish to consult with the author of this article, please feel free to contact Attorney Robert A. Hager at (330) 253–4925.


Holy Toledo! Claims Waived Under Article 8

In a February 2, 2016 decision, the Tenth District Court of Appeals in Franklin County affirmed the Court of Claims and upheld the decision to deny an electrical contractor’s claims against the University of Toledo because they were not timely asserted.

Board of Nursing Investigations: Survival Tips

One of the most sensitive relationships an advanced practice nurse (APN) holds in Ohio is with the Ohio Board of Nursing (“Board”). The Board holds regulatory authority over all Ohio licensed and certified APNs, registered nurses (RNs), licensed practical nurses (LPNs) and, most recently, dialysis technicians. It exists solely to enforce laws and rules that regulate the nursing profession in Ohio, and its top priorities are to efficiently license nurses in Ohio and to protect Ohio patients from dangerous practitioners. Over the past few years, we have seen an increase in disciplinary actions pursued by Ohio’s licensing boards, including the Ohio Board of Nursing. Between 2009 and 2011, the Board received 7,726 complaints including those related to substandard practice, drug theft, substance abuse, and patient abuse. Further, the approximately 2,503 licensees and certificate holders who were disciplined were assigned to Board staff for monitoring in 2010.

Brunell Chapter 11 ‘sign of the times’

Former Jacksonville Jaguars quarterback Mark Brunell’s Chapter 11 bankruptcy reorganization isn’t the first, and very likely won’t be the last, higher-income person seeking protection from creditors.

River health rates high on new Jacksonville City Council president’s list

River health rates high on new Jacksonville City Council president’s list Jack Webb said his year as Jacksonville City Council president will focus on the health of the St. Johns River, fiscal reform and revising the city charter. Webb acknowledged during his installation speech Thursday that leading the council through another tough financial year will be a challenge. “This is one of, if not, the most difficult times to be a public servant,” he said.

Changing Employers? Keep Your Tail Covered!

A common question regarding employment, and particularly changes in employment, revolves around the idea of tail insurance coverage. As such, this issue’s legal column explores what tail coverage is, why you need it, and who pays for it.