Ohio Court of Claims Explains Surety’s Obligations After Contractor Default

Blog Post

A surety thinking of funding its bankrupt principal for the purpose of completing a project should take notice of the recent decision in Jutte Elec., Ltd v. Ohio Facilitates Constr. Comm. In the January 17, 2016 decision, the Referee denied a surety’s claim of almost $1M for problems allegedly attributable to the project owner, the Ohio Schools Facility Commission (“OSFC”) (now known as the Ohio Facilities Construction Commission (“OFCC”)). The Referee rejected the surety’s claims on the grounds that the surety failed to prove that its damages were caused by the owner, and that it failed to give timely notice of its claims.

Jutte was the electrical contractor for this multi-prime project involving the construction of academic and dormitory buildings for the Ohio School for the Deaf and Blind. The Court’s decision makes clear that the project was, “[a] mess from the beginning to the end. It was poorly planned, poorly scheduled, poorly administered and…poorly performed.” Shortly after the project commenced, Jutte filed for bankruptcy and was declared in default by the owner, thus triggering an obligation by Jutte’s surety to investigate the claim and determine how to proceed.

As the Court’s decision points out, sureties typically have the right to choose their means and methods upon default of a principal so long as the owner is made whole.

Traditional options include:

  • Formally take over and contract for the project’s completion;
  • Allow the project to be defaulted, let the owner complete, and pay the reasonable costs to complete that are in excess of the contract price; or
  • Provide funds to an insolvent contractor to complete performance. After an extremely limited investigation, Jutte’s surety opted to complete the project by funding Jutte, its bankrupt principal. The Court made several key findings of fact, including (i) that the surety’s investigation was inadequate; (ii) its damages were a result of its inadequate investigation; (iii) the surety did not acquire Jutte’s contractual rights; and (iv) Jutte’s failure to give timely notice of its claims was imputed to the surety, barring the surety’s claims when it attempted to step into the shoes of its principal.

Sureties dealing with a defaulting contractor should be mindful of the key takeaways from this decision:

I. Surety’s Obligation to Adequately Investigate: Upon default, the surety should, at the very least:

  • Thoroughly investigate its underwriting file;
  • Interview its principal (contractor) and review its files;
  • Interview the project owner; and
  • Review all material which may demonstrate any problems on the project. A surety who fails to adequately investigate all project alternatives may be barred from recovery.

II. Rights of a Surety: The Jutte decision provides insight regarding the rights of a surety:

  • A surety’s decision to fund its bankrupt principal, as opposed to formally taking over the project, does not result in the surety obtaining the rights of the principal under the contract.
  • Absent clear evidence, an assignment of contractual rights to another party will not be found.

III. Waiver of Rights: A surety will be bound by a principal’s waiver or failure to give timely notice of its claims.

Should you wish to consult with the author of this article, Alex J. McCallion, Esq., please contact Brennan Manna Diamond’s construction law attorneys at (330) 253-5060.

Objections to the Decision have been filed by the parties and remain pending before the Court. BMD’s construction law attorneys will monitor the decision for future updates.

Ohio’s Statute of Repose: Is it Really a Bar to All Construction Claims?

In response to the increase in common-law claims against architects and contractors brought by third parties who lacked “privity of contract”, many states enacted a construction statute of repose. A statute of repose is intended to forever bar claims for certain injuries or damages after a set period of time following substantial completion. Subject to certain exceptions, the primary distinction between a statute of repose and statute of limitations is that a statute of repose begins to run regardless of whether one is aware of a defect.

Martin Pangrace and Catherine McCain Presenting at AIA Contract Document Workshop - September 26, 2017

BMD's Christopher Walker Helps Connect Veterans with Housing Options

Christopher Walker, a partner with BMD, is currently representing the Invest in America's Veterans Foundation, an organization that strives to provide a "head start" for veterans that involves the least amount of "red tape" possible.

Robert A. Hager Awarded the John Carroll University 2017 Alumni Medal

Robert A. Hager awarded the John Carroll University 2017 Alumni Medal

Duty to Preserve ESI: The Stakes Just Got Higher

A recent federal court decision highlights the potentially severe consequences for companies that do not take the proper steps to preserve electronically stored information (“ESI”) in anticipation of or in connection with litigation.