Holy Toledo! Claims Waived Under Article 8

News Article

In a February 2, 2016 decision, the Tenth District Court of Appeals in Franklin County affirmed the Court of Claims and upheld the decision to deny an electrical contractor’s claims against the University of Toledo because they were not timely asserted.

This ruling sends another important message to contractors that you must provide both timely notice and substantiation of your claims or they will be waived.

Article 8 of the State of Ohio General Conditions sets forth the requirements for submitting and substantiating a claim:

  1. claims accrue on the date of the occurrence of the event giving rise to the claim;
  2. within 10 days after the claim accrues, the contractor must provide written notice to the contracting authority and architect/engineer;
  3. within 30 days after initiating a claim the contractor must provide 4 copies of supporting documentation to substantiate the claim;
  4. within 30 days after initiating the claim the contractor must certify the claim by providing a notarized statement verifying the accuracy, completeness, fairness and reasonableness of the claim and claim amount; and
  5. failure to timely comply with requirements 2, 3 or 4 above will constitute an “irrevocable waiver” of any related claim.

Despite the contractor’s arguments of substantial compliance, owner-caused delays, contractor inability to calculate the precise amount of its damages and futility of administrative remedies, the Court of Claims and Court of Appeals strictly interpreted the contractual notice provisions and held that the electrical contractor had irrevocably waived its claim as a matter of law. Relief in the form of unjust enrichment was also denied. Holy Toledo! That hurts Batman! POW!

Lessons learned:

  1. understand and follow dispute resolution requirement in your construction contract;
  2. obtain assistance from legal counsel, risk management or a claims consultant to prepare and deliver a timely, properly documented and certified claim;
  3. failure to strictly comply with the contract requirements can be costly and painful; and
  4. be proactive, not reactive.

Should you wish to consult with the author of this article, please feel free to contact Attorney Robert A. Hager at (330) 253-4925.


Ohio Supreme Court Liquidated Damages Analysis: Hindsight is not 2020!

In a case decided on February 24, 2016, the Ohio Supreme Court construed the enforceability of a liquidated damages provision in a public works construction contract. The Court held that when evaluating the enforceability of a liquidated damages provision in a construction contract, the court must conduct its analysis prospectively, based on the per diem amount of the liquidated damages at the time the contract is executed, and not retrospectively, based on the total amount of liquidated damages that ultimately accrue.

Board of Nursing Investigations: Survival Tips

One of the most sensitive relationships an advanced practice nurse (APN) holds in Ohio is with the Ohio Board of Nursing (“Board”). The Board holds regulatory authority over all Ohio licensed and certified APNs, registered nurses (RNs), licensed practical nurses (LPNs) and, most recently, dialysis technicians. It exists solely to enforce laws and rules that regulate the nursing profession in Ohio, and its top priorities are to efficiently license nurses in Ohio and to protect Ohio patients from dangerous practitioners. Over the past few years, we have seen an increase in disciplinary actions pursued by Ohio’s licensing boards, including the Ohio Board of Nursing. Between 2009 and 2011, the Board received 7,726 complaints including those related to substandard practice, drug theft, substance abuse, and patient abuse. Further, the approximately 2,503 licensees and certificate holders who were disciplined were assigned to Board staff for monitoring in 2010.

Brunell Chapter 11 ‘sign of the times’

Former Jacksonville Jaguars quarterback Mark Brunell’s Chapter 11 bankruptcy reorganization isn’t the first, and very likely won’t be the last, higher-income person seeking protection from creditors.

River health rates high on new Jacksonville City Council president’s list

River health rates high on new Jacksonville City Council president’s list Jack Webb said his year as Jacksonville City Council president will focus on the health of the St. Johns River, fiscal reform and revising the city charter. Webb acknowledged during his installation speech Thursday that leading the council through another tough financial year will be a challenge. “This is one of, if not, the most difficult times to be a public servant,” he said.

Changing Employers? Keep Your Tail Covered!

A common question regarding employment, and particularly changes in employment, revolves around the idea of tail insurance coverage. As such, this issue’s legal column explores what tail coverage is, why you need it, and who pays for it.