In a February 2, 2016 decision, the Tenth District Court of Appeals in Franklin County affirmed the Court of Claims and upheld the decision to deny an electrical contractor’s claims against the University of Toledo because they were not timely asserted.

This ruling sends another important message to contractors that you must provide both timely notice and substantiation of your claims or they will be waived.

Article 8 of the State of Ohio General Conditions sets forth the requirements for submitting and substantiating a claim:

  1. claims accrue on the date of the occurrence of the event giving rise to the claim;
  2. within 10 days after the claim accrues, the contractor must provide written notice to the contracting authority and architect/engineer;
  3. within 30 days after initiating a claim the contractor must provide 4 copies of supporting documentation to substantiate the claim;
  4. within 30 days after initiating the claim the contractor must certify the claim by providing a notarized statement verifying the accuracy, completeness, fairness and reasonableness of the claim and claim amount; and
  5. failure to timely comply with requirements 2, 3 or 4 above will constitute an “irrevocable waiver” of any related claim.

Despite the contractor’s arguments of substantial compliance, owner-caused delays, contractor inability to calculate the precise amount of its damages and futility of administrative remedies, the Court of Claims and Court of Appeals strictly interpreted the contractual notice provisions and held that the electrical contractor had irrevocably waived its claim as a matter of law. Relief in the form of unjust enrichment was also denied. Holy Toledo! That hurts Batman! POW!

Lessons learned:

  1. understand and follow dispute resolution requirement in your construction contract;
  2. obtain assistance from legal counsel, risk management or a claims consultant to prepare and deliver a timely, properly documented and certified claim;
  3. failure to strictly comply with the contract requirements can be costly and painful; and
  4. be proactive, not reactive.

Should you wish to consult with the author of this article, please feel free to contact Attorney Robert A. Hager at (330) 253-4925.


Daphne Saneholtz Discusses ACA Repeal and Effects on Ohioans

The latest roadblock in efforts to dismantle the Affordable Care Act has many Ohioans living with HIV and AIDS relieved, but still concerned about what's next.

New Akron Legislation Aims to Increase Income Tax Revenue Through Construction Contractor Registrations

The City of Akron recently passed three new pieces of legislation aimed at boosting city coffers by requiring contractors to take additional steps prior to performing work in the city.

BMD Recognized for Health Law Practice

“Ever since its founding in 2000, attorneys at Brennan, Manna & Diamond have focused on offering a full range of services to all the firm’s clients, including developing industry-specific practice areas like healthcare,” said Matt Heinle, co-managing partner at the firm.

Defining Concierge and Boutique Medicine

Amanda L. Waesch, Partner at Brennan, Manna & Diamond, LLC, Akron, Ohio, shared with the Stark County Medical Society Membership alternative physician practice structures, pros and cons of each structure, and the differences between Institutional Providers and Concierge Medicine.

How artificial intelligence relates to the legal profession

Legal research has changed. An attorney who started his career dredging through books can now instantly consult vast databases, saving countless man hours. Soon, however, it may need not involve the man at all.